PMP (Project Management Professional) is a leading certification offered by PMI (Project Management Institute, US) for project managers across the world. pmp certification is the Gold Standard for project management professionals in the fields of IT, ITES, Power, Energy, Automotive, BioTech, Infrastructure &
Public Sector. The number of PMP practitioners saw a cumulative growth of 146% over three years – from 94,356 in 2004 to 242,000 in 2007.

PMP practitioners earn highest salaries among all IT workers: Certification Magazine 2006 Annual Salary Survey
Among ‘10 Hottest IT certifications’ for 3 consecutive years: CertCities.com 2006 Annual Survey

Aptech is a PMI-authorized Registered Education Provider (REP). This means that PMP Training delivered by Aptech is accepted by PMI as the requisite training experience for qualifying to appear for the PMP Examination.

AGLSM SDN BHD (736891-H)
3.03D, 3rd Floor
Kompleks Antarabangsa
Jalan Sultan Ismail
50250 Kuala Lumpur
MALAYSIA.

Tel: +603 – 2711 0373
Fax: +603 – 2711 0372
Email: enquiry_msia@aptech.ac.in

Duration : 0:7:19

Read the rest of this entry »

Technorati Tags: , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,

Jul 2

Claudia Baca provides suggested day-by-day activities that you should perform the week of your PMP Exam.

Lesson 16 from, Project Management for Mere Mortals (Video Training): The Tools, Techniques, Teaming, and Politics of Project Management

ISBN: 978-0-321-50919-2

http://www.informit.com/store/product.aspx?isbn=0321509196

Duration : 0:8:47

Read the rest of this entry »

Technorati Tags: , , , , , ,

Jun 17

Lets look at this example. There are basically 5 activities in this Project.
If you look at the Network diagram, there are two paths in this Network.
Start, 1, 2, 4, 5, End is one path and Start, 1, 3, 5, End is the second path. Since the duration of the path Start, 1, 2, 4, 5, End is 18 days, which is more than the duration of the path Start, 1, 3, 5, End. The critical path of the Project is Start, 1, 2, 4, 5, End.
Take some time to calculate all the four values, i.e. Early Start, Early Finish, Late start and late finish of the activities. I have written down the values for your verification.
Let me take Activity 3 as an example.
First we will calculate the Early Start and Early Finish dates.
Activity 3 can start only after Activity 1. Since the Early finish of Activity 1 is 3, which becomes the Early Start of Activity 3.

Activity 3 can not start earlier than 3, because Activity 1 is getting completed only than.
So, Early Start of Activity 3 is 3. Since the duration of the activity is 6 days. The Early Finish of Activity 3 is 3+6= 9 days.
Now, lets calculate the late start and late finish of Activity 3.
Late Start of Activity 5 is 14 days. The activity 3 happens just before Activity 5, so the Late Finish of Activity 3 is 14 days. To calculate the late start, you can subtract the duration from late finish. So the Late start of Activity 3 is 14-6=8.

Duration : 0:2:42

Read the rest of this entry »

Technorati Tags: , , , , , , , , ,

Jun 4

Sir Ganttalot helps you prepare for the PMP exam by explaining Three-Point Estimating. The video explains how to derive a Mean Estimate, how to calculate Standard Deviation (Sigma), and how to calculate Variance. In all cases both Triangular and PERT techniques are addressed. A second, related, video then shows how to apply Sigma values to calculate Confidence Levels for Estimates

Duration : 0:9:37

Read the rest of this entry »

Technorati Tags: , , , , , , , , , , , , , , , , , , , , , , , , , ,

May 23

http://www.praizion.com

EARNED VALUE BASICS – Solving problems and looking at the basic formulas for EV metrics.

The projects I used EVM had defined points in the project where different % percentages were claimed as complete. A project could be broken down at the Project Manager’s discretion into:
Milestone 1 – 20% complete
Milestone 2 – 50% complete
Milestone 3 – 30% complete

The PM has to decide at what point to claim work as complete and how much will be claimed. The success in EVM implementation revolves around accurate Budgeting (BAC) and the breakdown into PV for the relevant time periods and also BCWP (EV itself) the work has to be Budgeted as accurately as possible.

Sometimes the work is under budgeted which gives inaccurate EV metrics.

You may refer to this article: http://en.wikipedia.org/wiki/Earned_value_management
For extra reading. Also there is a study material Earned Value Basics 2 on the LMS for further study.

Duration : 0:8:0

Read the rest of this entry »

Technorati Tags: , , , , , , , , , , , ,

May 5

Project Management Certification is for professionals looking to become certified in Project Management as a Project Management Professional (PMP) or Certified Associate in Project Management (CAPM). Project Management is a set of skills which includes budget and time awareness, communication and presentation skills, logical process skill, and more.
In this program students will learn the techniques of planning, developing, deploying, and completing a project. These techniques will be enhanced with Microsoft Project software application training in Microsoft Project Level 1 & Microsoft Project Level 2; Microsoft PowerPoint Introduction & Microsoft Office PowerPoint Intermediate; and Microsoft Office Visio Level 1. These software applications along with training on presentation and organizational skills will help beginning through experienced project managers prepare for PMIĀ® industry recognized certification, improve career potential, and become an important asset to any company. Industry recognized certifications from the Project Management Institute (PMI) offer individuals enhanced career opportunities. The Certified Associate in Project Management (CAPM) is a Project Management Certification for those starting their project management profession. Upon completing our 8 week program, students will have acquired the concepts and fundamentals to become a project manager. The Project Management Professional (PMP) is designed as a study aid and professional development tool for existing Project Managers. Through the combination of the pmp certification Prep course, Project Fundamentals course, and application skills both new and experienced Project Managers will gain valuable skills for everyday work as well as prepare for their respective certification exams.

Duration : 0:1:56

Read the rest of this entry »

Technorati Tags: , , , , , , , ,

May 2

Project Scope Management Lecture 10

Duration : 0:6:41

Read the rest of this entry »

Technorati Tags: , , , , , , , ,

May 2

PMP Exam Project Scope Management Lecture 6

Duration : 0:9:59

Read the rest of this entry »

Technorati Tags: , , , , , , ,

Apr 29

WWW.PRAIZION.COM
10 MINUTE EXCERPT FROM THE CD: DEMYSTIFYING THE PMBOK GUIDE 4TH EDITION – PMP EXAM PREP

A SUCCINT 35 MINUTE HIGH LEVEL TURBO DRIVE THROUGH THE PMBOK GUIDE 4TH EDITION
EXPLAINING:

THE PMI
CAPM, PMP, PGMP CERTS
PMI GLOBAL FOOT PRINT
MEMBERSHIP
WHY PMP?
THE PMBOK GUIDE
KNOWLEDGE AREAS
PROCESS GROUPS
ALL 42 PROJECT MANAGEMENT PROCESSES IN THE 4TH EDITION

Duration : 0:9:47

Read the rest of this entry »

Technorati Tags: , , , , , , , , , , , , ,

Apr 26

A brief walk through of the latest version of our PMP Exam Simulator. Also available for Java, PHP, Network, and EA certification exams. The best bang for your bucks! The others cost hundreds more!

Duration : 0:9:8

Read the rest of this entry »